Public Consultation Meeting 1
Concrete gravity base (CGB) decommissioning
- Concept assessment process explained
- Preliminary decommissioning concepts outlined
- Continuing consultation process proposed
- Stakeholder views noted
See published Meeting Report dated 21st January 2010. -
Begin website publication of initial study results
- CGB refloat assessment
- Platform re-use assessment
-
Publish summary of updated CGB decommissioning concepts
-
Publish Dunlin decommissioning programme document architecture
-
Publish summary of CGB decommissioning option selection
-
Public Consultation Meeting 2
Preliminary decommissioning concepts for:
- Dunlin platform topsides
- Osprey subsea facilities
- Merlin subsea facilities -
Publish decommissioning concept selection
-
Public Consultation Meeting 3
-
Commission Decommissioning Environmental Impact Assessment
-
Publish results of Environmental Impact Assessment
- Initiate public consultation process
-
Formal submission of Dunlin Decommissioning Programme to DECC
-
Dunlin Cluster Decommissioning Programme approval for Dunlin, Osprey and Merlin fields