Marston Notified of Leak
via Phone Call from David -
MBH Enters Unit
Ceiling was cut open on both levels and covered with trash bags -
Reached out regarding Roaches
via email; MBH said they would send the exterminator again -
Notified that the roof was leaking again
via email -
Sent Email Notifying of Escrow
Included screenshots of escrow account -
Followed up on escrow email
-
Sent Video of Ceiling Hole
-
Sent Health Code Provision
Sent an email regarding additional escrow and ISD plans if not repaired -
Skylight Chaulked
Sent "new contractor" Mark becuase prior contractor Mike's "bid was high" ... Not a roofer; just put chaulk around the skylight -
Sent update following 12/27 Visit
-
Sent 93A Demand Letter
First of 2 -
Sent Updated 93A Letter
-
93A Response Received
-
Requested ISD Inspection
-
ISD Inspection Date
-
ISD Notice Served on Marson
-
Marston begins to seal hole
No final repair to the actual underlying leak (as required by ISD Report) -
Fire Alarms Brought up to Code & Hole Covered with Drywall
-
Notified Creed & Formica of the ISD Report
-
NTQ Sent by Sheriff's Office
-
Summary Process Summons and Complaint Sent by Sheriff