Bricks Team - Timeline

  • Sprint 0 START (Project Kickoff)

  • Period: to

    OSLC: Onboarding and Definition

  • Orlando, Andres, Fabian: Onboarding starts!

  • David: Onboarding starts!

  • Sprint 0 END

  • Sebastian: Onboarding starts

  • Sprint 1 START

  • Planning (Sprint 1)

    3 hrs - Goals:
    1 - Finish Onboarding
    2 - Complete POC review / Start Prototype
    3 - QA has a strong perspective based on Jeet data
  • Period: to

    OSLC Dev Sprints

  • Orlando, Andres, Fabian: Onboarding complete

    All onboarding tasks complete and closed
  • MILESTONE: Finish Prototype design

    Finish and send Prototype design to team +Sean
    This gives enough time to review before Refinement
  • Refinement and Story Building

    2-3 hrs - Goals:
    Discuss Prototype plan and create all stories needed to accomplish.
    Proactively plan and create 1st Rev service using Basic Auth and no Admin interface
    Define QA activities for the next Sprint (QA should bring actions to meeting)
  • David, Sebast: Onboarding Complete

    All onboarding tasks complete and closed
  • MILESTONE: Finish and Demonstrate Prototype build

    Prototype is complete, Team Demo to Stakeholders, and influencing design and stories in the next sprint
  • 1st Rev Mini-refinement

    1.5 hrs - Goal:
    Refine and write stories in prep for Planning (Sprint 2)
  • Sprint 1 END

  • Planning (Sprint 2)

    3 hrs - Goals:
    TENTATIVE - 1st rev Service creation with basic auth and no admin interface
  • Sprint 2 START

  • Oscar - Onboarding Starts

  • MILESTONE: Finish and Demonstrate 1st Rev

    TBD
  • Sprint 2 END

  • Planning (Sprint 3)

    3 hrs - Goals:
    TENTATIVE - Add Oauth1, Start rough Admin UI
  • Sprint 3 START

  • Oscar: Onboarding complete

    All onboarding tasks are complete and closed
  • Sprint 3 END