![Parklane buttons 01](https://s3.amazonaws.com/s3.timetoast.com/public/uploads/photos/10558930/Parklane_buttons-01_medium_square.png?X-Amz-Algorithm=AWS4-HMAC-SHA256&X-Amz-Credential=AKIAJB6ZCNNAN7BE7WDQ%2F20240813%2Fus-east-1%2Fs3%2Faws4_request&X-Amz-Date=20240813T232404Z&X-Amz-Expires=604800&X-Amz-SignedHeaders=host&X-Amz-Signature=9c2c2bae67f1aaa6e63e504c00961d3400f4fea80184328349ee32999e804da6)
Parklane Landscaping Corporation - Stone Mountain HOA Front Entry Monument Revitalization Timeline
By Parklane
-
Period: to
Demolition Phase
Removal of plant material (excluding large oaks and sculpted Pride of Houston Yaupon); Mid-sized oak tree at light pole to be removed; Removal of rocks (to be placed at side entrance to be repurposed by HOA); Removal of old irrigation system and parts; Careful conservation of electricity lines and main irrigation lines; -
Period: to
Turf and Soil Removal
Removal of current sod (turf); removal excess soil (berms); Excavation/Preparation for installation of fresh nutrient-rich soil (4-6 inches deep) -
Period: to
Tree Pruning, Canopy Opening, Shaping
Manicuring and pruning of the oak trees to allow for increased light and richer growth ( to include oak tree moss removal). -
Period: to
Internal Limestone Outline Review by Landscape Committee
The board/landscape committee will review the final outline of the limestone border and approve the layout design before installation. -
Period: to
Nutrient-Rich Soil Installation
Installation of Nutrient-Rich Soil -
Period: to
Limestone Curbing for Oak Tree Beds Installation
Limestone curb to be installed per approval by board -
Period: to
Irrigation Installation
Landscape irrigation installation per landscape planting plan. -
Period: to
Grass Installation
Zoysia Turf Grass installation -
Period: to
Plant Material and Mulch Installation
Installation plant material at entry monument and spreading of mulch in design specified areas (entry bed and tree beds)