Review Reports and File Feed Transition Strategy
9 months prior to transition date -
Meet with Customer to Talk about Transition
8 months prior to transition -
Submit Ticket for File Feed Work and NSR for any Report Customizations
7 months prior to transition date -
File Feed Work Begins - Customer and Hartford Resources Assigned to Implement
6 months prior to transition date -
Establish Standard On-Demand Report Deliver or other Options (TLS/MFT) - Submit Ticket as Appropriate for TLS/MFT Delivery Options
5 months prior to transition date -
Ensure any Custom Reporting Work is on Track to be Completed by go-Live Date
2 months prior to transition date