par2

  • Initial requirements from Paris staff

    Bug 751981
  • Site Survey

    Discussions with Paris staff about requirements
  • Identify ISP

    Started calling all available ISPs to see if they serviced the area and to identify terms. Learned neighbor, IS-cool, was not willing to share thier 100M service. Learned there was no provisioned phone line for the space, but IS-cool would provide copper.
  • ISP Selected

    OVH selected as ISP based on price, available bandwidth, and time to install. IS-cool investigates if they can find bandiwdth to share. Order cannot be placed until POTS is available
  • Identify Copper Pairs

    France Telecom (FT) claims copper is on Floor 2. IS-cool cannot confirm.
  • Request Phone Line

    The space is IS-cool's so they need to order the phone line.
  • Phone Line Order Confirmed

    IS-cool confirms they ordered the phone line.
  • Install Update Inquiry

    IS-cool says a tech will arrive May 5
  • IT Update

    Tristan asks about IT setup and is told it will be about 3 weeks for everything to be installed (firewalls, switches, admin hosts)
  • Phone Line Status

    Checked in about phone line install. Got conditional approval to borrow bandiwdth from neighbor.
  • Phone Line Delay

    Is-cool discovers there is no copper. They decided to run copper from their floor rather than home running new cable because of costs. This method required boring hole between walls.
  • Shared Bandwidth Test

    Configuration and test of the shared Internet with Is-cool
  • Early June Move In Estimate

    It was aksed when staff could move in and the response was, "It's to be decided. Early June is my rough estimate." https://bugzilla.mozilla.org/show_bug.cgi?id=751981#c5
  • Period: to

    Arzhel in States for Work Week

  • Staff Move In Early

    Staff already in the temporary location and are complaining Wifi is sub-optimal. https://bugzilla.mozilla.org/show_bug.cgi?id=755333
  • Cable Identified

    Dan noticed the cable hanging from the wall and ask Is-cool if it is ready for final install
  • Period: to

    In-cool IT on Vacation

  • Phone Line Delay

    Dan mets their IT contact, line is ready but they need to cancel a subscription on that line https://bugzilla.mozilla.org/show_bug.cgi?id=751981#c9
  • Wireless Troubleshooting

    Arzhel takes train from LON to debug wireless. Brings equipment from LON.
  • DSL Ordered

    DSL ordered. Tech visit scheduled for June 4. Shared internet becomes unstable
  • Troubleshooting of Shred Service

    In-cool calls ISP to troubleshoot usse
  • Mozilla Disconnected from In-cool

    Email from In-cool says the configuration they have for sharing the connection with us is causing instability.
  • DSL Billing Questions

    It is unclear if the DSL order was compelted because Arzhel sent paperwork to get direct debit established which was resolved same say.
  • Delay

    Arzhel offers Mozilla assisance with configuration DSL tech does not show up