Period: to
Preparing site wk1
Starts Monday 2nd of January 2017
5 days -
Period: to
Preparing site wk2
5 days -
Period: to
Plumbing
3 days of pluming -
Period: to
Slab
2 days -
Period: to
Frame wk1
5 days -
Period: to
Frame wk 2 part 1
2 days -
Period: to
Frame wk 2 part 2
3 days -
Period: to
Frame wk 3
5 days -
Period: to
Frame wk 4
5 days -
Period: to
Windows
2 days -
Period: to
Roof
3 days -
Period: to
Cladding frame part 1
1 day -
Period: to
Cladding frame part 2
2 days -
Period: to
Cladding frame part 3
2 days -
Period: to
Electrical
8 hours -
Period: to
Internal wall lining
4 days -
Period: to
Waterproofing
1 day -
Period: to
Tiling wet areas
5 days -
Period: to
Fixtures and fittings
3 days -
Period: to
Timber flooring
6 hours -
Period: to
Carpet flooring
8 hours -
Period: to
Painting Internally part 1
5 days -
Period: to
Painting externally part 1
5 days -
Period: to
Painting externally part 2
1 day -
Period: to
Painting internally part 2
3 days -
Period: to
Landscaping and driveway part 1
2 days -
Period: to
Fence part 1
2 days -
Period: to
Landscaping and driveway part 2
3 days -
Period: to
Fence part 2
1 day