House construction

  • Period: to

    Preparing site wk1

    Starts Monday 2nd of January 2017
    5 days
  • Period: to

    Preparing site wk2

    5 days
  • Period: to

    Plumbing

    3 days of pluming
  • Period: to

    Slab

    2 days
  • Period: to

    Frame wk1

    5 days
  • Period: to

    Frame wk 2 part 1

    2 days
  • Period: to

    Frame wk 2 part 2

    3 days
  • Period: to

    Frame wk 3

    5 days
  • Period: to

    Frame wk 4

    5 days
  • Period: to

    Windows

    2 days
  • Period: to

    Roof

    3 days
  • Period: to

    Cladding frame part 1

    1 day
  • Period: to

    Cladding frame part 2

    2 days
  • Period: to

    Cladding frame part 3

    2 days
  • Period: to

    Electrical

    8 hours
  • Period: to

    Internal wall lining

    4 days
  • Period: to

    Waterproofing

    1 day
  • Period: to

    Tiling wet areas

    5 days
  • Period: to

    Fixtures and fittings

    3 days
  • Period: to

    Timber flooring

    6 hours
  • Period: to

    Carpet flooring

    8 hours
  • Period: to

    Painting Internally part 1

    5 days
  • Period: to

    Painting externally part 1

    5 days
  • Period: to

    Painting externally part 2

    1 day
  • Period: to

    Painting internally part 2

    3 days
  • Period: to

    Landscaping and driveway part 1

    2 days
  • Period: to

    Fence part 1

    2 days
  • Period: to

    Landscaping and driveway part 2

    3 days
  • Period: to

    Fence part 2

    1 day