Recieve Notice to Proceed with Construction
-
Period: to
Engineer Set Grading Limits
-
Period: to
Demolish Concrete Pads
-
Period: to
Excavate Building Pad
-
Insight Park Breaks Ground
-
Period: to
Vibro Stone Columns
-
Period: to
Spread Footings East Wing
-
Period: to
Spread Footings Central
-
Period: to
Spread Footings West Wing
-
Period: to
Underslab Plumbing East Wing
-
Period: to
East Wing Column Piers with Anchor Bolts
-
Period: to
Underslab Electrical Central
-
Period: to
Foundation Walls West Wing
-
Period: to
Underslab Plumbing Central
-
Period: to
Grade Beams East Wing
-
Period: to
Underslab Electrical West Wing
-
Period: to
Underslab Plumbing West Wing
-
Period: to
West Wing Column Piers with Anchor Bolts
-
Period: to
Edge Form & Fine Grade Slab East Wing
-
Period: to
Column Piers with Anchor Bolts West Wing
-
Period: to
Vapor Barrier/Reinforcing at Slab East Wing
-
Period: to
Grade Beams West Wing
-
Period: to
Erect Steel Columns East Wing
-
Period: to
Elevator Pit
-
Period: to
Erect Castellated Beams East Wing
-
Period: to
Vapor Barrier/Reinforcing at Slab West Wing
-
Period: to
Pour Slab On Grade West
-
Period: to
Install Steel Deck East Wing
-
Period: to
Column Piers with Anchor Bolts at Central
-
Period: to
Column Piers with Anchor Bolts at Central
-
Period: to
Grade Beams at Central
-
Period: to
Pour 2nd Floor Slab East Wing
-
Period: to
Erect Steel Columns West
-
Period: to
Castellated Beams West Wing
-
Period: to
Exterior Stud Framing 1st Floor at East Wing
-
Period: to
Erect Steel Columns Central
-
Period: to
Erect Castellated Beams Central
-
Period: to
Install Steel Joists East Roof
-
Period: to
Install Steel Deck West
-
Period: to
Exterior Stud Framing 2nd Floor
-
Period: to
Install Perimeter Bent Plate at East Roof
-
Period: to
Exterior Stud Framing 1st Floor Central
-
Period: to
Exterior Stud Framing 1st Floor at West Wing
-
Period: to
Install Duct Work 1st Floor East Wing
-
Period: to
Install Metal Stud Framing 1st Floor at West Wing
-
Period: to
Install Metal Stud Framing 1st Floor Central
-
Period: to
Window Blocking 1st Floor at East Wing
-
Period: to
Erect Steel Stairs
-
Period: to
Install Mechanical and Roof Opening Support Frames
-
Period: to
Window Blocking 2nd Floor at East Wing
-
Period: to
Window Blocking 1st Floor Central
-
Period: to
Window Blocking 1st Floor at West Wing
-
Period: to
Erect Beams at Central/West Roof
-
Period: to
Install Metal Stud Framing 2nd Floor East Wing
-
Period: to
Install Steel Deck Central
-
Period: to
Window Blocking 2nd Floor Central
-
Period: to
Window Blocking 2nd Floor at West Wing
-
Period: to
Install Duct Work 1st Floor Central
-
Period: to
Install Duct Work 1st Floor at West Wing
-
Period: to
Install Perimeter Bent Plate at Central/West Roof
-
Period: to
Install Metal Roof Deck Central/West Roof
-
Period: to
Install Windows & Curtain Wall East Wing
-
Period: to
Install Windows & Curtain Wall Central/West Wing
-
Period: to
Install Metal Stud Framing 2nd Floor Cent/West Wing
-
Period: to
Install Roof Drain/Penetration at Roof Deck East
-
Period: to
Install Duct Work 2nd Floor Central/West Wing
-
Period: to
Pour 2nd Floor Slab Central
-
Period: to
Install Tapered Roof Insulation & Crickets East Roof
-
Period: to
CMU Elevator Shaft 2nd to Roof
-
Period: to
Foil Face Insulation 1st Floor at East Wing
-
Period: to
Install Roof Drain/Penetration at Roof Deck West
-
Period: to
Install Mechanical Piping 1st Floor East Wing
-
Period: to
Install Mechanical Piping 1st Floor Cent/West Wing
-
Period: to
Install Mechanical Piping 2nd Floor East Wing
-
Period: to
Install Mechanical Piping 2nd Floor Central/West Wing
-
Period: to
Insulation & Drywall 1st Floor Central/West Wing
-
Period: to
Install Brick/Stone 1st Floor at East Wing
-
Period: to
Install Brick & Stone 2nd Floor at East Wing
-
Period: to
Install Lightning Protection West Roof
-
Period: to
Install Lightning Protection East Roof
-
Period: to
Install Heat Pumps 1st Floor East WIng
-
Period: to
Install Heat Pumps 2nd Floor East Wing
-
Period: to
Install Plumbing Equipment in Mechanical Room 1st Floor
-
Period: to
Install Heat Pumps 2nd Floor Central/West Wing
-
Period: to
Install Heat Pumps 1st Floor Central/West Wing
-
Period: to
Insulation & Drywall 2nd Floor Central/West Wing
-
Period: to
Insulation & Drywall 1st Floor East Wing
-
Period: to
Install Brick/Stone1st Floor at Central/West Wing
-
Period: to
Demo & Grading at Connection to Intramural
-
Period: to
Install Roof Top Mechanical Equipment
-
Period: to
Finish Drywall 1st Floor Central/West Wing
-
Period: to
Finish Drywall 1st Floor East Wing
-
Period: to
Finish Drywall 2nd Floor East Wing
-
Period: to
Insulation & Drywall 2nd Floor East Wing
-
Period: to
Install Sun Shades South Elevator East Wing
-
Period: to
Prime/Paint 1st Coat 1st Floor East Wing
-
Period: to
Install Sun Shades South Elevator West Wing
-
Period: to
Prime/Paint 1st Coat 2nd Floor East Wing
-
Period: to
Hang & Finish Drywall Ceilings 1st Floor Central/West
-
Period: to
Hang & Finish Drywall Ceilings 2nd Floor Central/West
-
Period: to
Install Elevator Beam, Rails, Ladders and Equipment
-
Period: to
Install Elevator Car
-
Period: to
Prime/Paint 1st Coat 2nd Floor Central/West Wing
-
Hook Up Permanent Power
-
Period: to
Install Elevator Cab Finishes
-
Period: to
Install Louver Equipment Screen at High Roof East
-
Period: to
Install Louver Equipment Screen at High Roof West
-
Period: to
Stone Base at Connection to Intramural
-
Period: to
Install Elevator Door Frames
-
Period: to
Asphalt Paving at Connection to Intramural
-
Period: to
Open Temporary Road
-
Period: to
Install Doors & Hardware 1st Floor East Wing
-
Period: to
Porcalin Tile & Terrazzo 1st Floor Central/West Wing
-
Period: to
Install Doors & Hardware 2nd Floor East Wing
-
Period: to
Install Roller Shades 1st Floor Central/West Wing
-
Period: to
Install Doors and Hardware 1st Floor Central/West Wing
-
Period: to
Final Paint 1st Floor East WIng
-
Period: to
Install Roller Shades 2nd Floor Central/West Wing
-
Period: to
Demo & Grading at Connection to Hawthorne Road
-
Period: to
Install Carpet 1st Floor Central/West Wing
-
Period: to
Final Paint 2nd Floor East Wing
-
Period: to
Install Doors & Hardware 2nd Floor Central/West Wing
-
Period: to
Aspahlt Paving at Connection to Hawthorne Road
-
Period: to
Landscaping and Signage Allowance
-
Period: to
Traffic Striping and Signage at Connections
-
Open New Intrmural Road
-
Period: to
Final HVAC Start Up with Geothermal
-
Period: to
Final Commissioning/Test Ballance
-
Period: to
Final Inspections/Punchlist
-
Building Substantially Complete
-
Insight Park Opens 1st Building
-
Grand Opening of Insight Park