-
River Crossing Study
River Crossing Study is performed indentifying the composition of three bore holes in the proposed area of the Rianila River HDD (HOC 8) -
Contracts
Parties enter into contracts -
Meetings
Meetings held in Toronto from 7/30 to 7/31 to clarify responsibilities of the parties -
Geotechnical Prospective Report
SLI issues Geotechnical Prospective Report to CCG, informing it of presence of rock at HDD 2 and HDD 3 -
Borehole Date
SLI issues borehole date in relation to HDD 3 (HOC 3) -
ECN 43
SLI issues ECN 43 regarding extension of 36" HDPE pipe (HOC 15) -
MOU 1
New completion date set for 9/30/2009; payment made to resolve CCG's claims -
Erosion Control
SLI confirms that quantities of erosion control beyond those found in the bid proposal will be paid at the Contract (HOC 1.3) -
ECN
SLI issues ECN regarding potential change in the distribution line (HOC 13) -
Period: to
TMF Road Restrictions
Restrictions in place on access to TMFroad from June through September (HOC 7) -
MOU 2
Contract converted to lumpsum; all claims released; time for completion revised to 12/31/209;established requirement of tranche payments if CC and MC reached by 12/31/2009 and 3/31/2010 (HOC 4) -
Employee Fatality
Employee fatalityt occurs on Tailings Road (HOC 5) -
Beginning of Work Suspension
SLI suspends work due to 7/2/2009 fatality (on all locations other than Tailings Road, suspension ends 7/9/2009) (HOC 5) -
End of Work Suspension
SLI suspends work due to 7/2/2009 fatality (on all locations other than Tailings Road, suspension ends 7/9/2009) (HOC 5) -
Back Charges
SLI expresses intent to apply back charges incurred prior to signing of MOU 2 (HOC 2) -
Sahtandra River Crossing
SLI issues drawing confirming that Shatandra River crossing is to be performed by open-cut method (HOC 14) -
Violation of MOU 2
CCG informs SLI that it views the incorporation of pre-MOU 2 backcharges to be a violation of MOU 2 (HOC 2) -
Vakona Road Work
CCG performs work on Vakona Road (HOC 16) -
Floating Bridge Inaccesible
Floating bridge at AR10 inaccessible due to rain (HOC 10) -
Vakona Road Request
CCG revieves verbal request to return Vakona Road to equal or better condition than when work started (HOC 16) -
Work Suspension (8/8-8/13)
SLI suspends work due to lack of ambulance coverage (HOC 5) -
Locals Prevent Access (8/12-8/13)
Access prevented by locals at AR2 (HOC 12) -
Hard Rock Encounter
CCG advises SLI that unexpected hard rock has been encountered at HDD 3 (HOC 3) -
Distribution Line Change
SLI issues formal instruction regarding change to the distribution line (HOC 13) -
Locals Prevent Access (9/26-9/30)
Access prevented by locals at AR7 (HOC 12) -
Period: to
14 km of reinstatement
CCG performs 14 km of reinstatement (KP 0-12, 16-18) purusant to October 2009 design drawings, which must subsequently be re-worked following 12/15/2009 design changes -
Floating Bridge Inaccesible (10/24-10/27)
Floating bridge at AR10 inaccessible due to rain (HOC 10) -
Distribution line and MOU 2
SLIinforms CCG that costs associated with changes to the distribution line were included within the MOU 2 lump sum price -
FLoating Bridge Inaccessible (11/21-11/24)
Floating Bridge at AR10 inaccessible due to rain (HOC 10) -
Re-Vegitation measure
SLI instructs CCG to plant vetiver grass as permanent re-vegetation measure on ROW slopes (HOC 1.1) -
Floating Bridge Inaccessible (11/26-11/29)
Floating bridge at AR10 inaccessible due to rain (HOC 10) -
Re-Design
SLI provides design showing significant re-profiling of the ROW (HOC 1.2) -
Hydrotesting failure
Hydrotesting failure occurs along Section 8 of the slurry pipeline (KP 82-KP94) (HOC 11) -
Delay (12/21-12/31)
Delays occur from AR7-AR9 due to hydrotesting failure -
Open-Cut Method Delay
CCG informs SLI that SLI's choice of open-cut method for the Sahatandra River crossing has resulted in delay (HOC 14) -
Re-Vegitation Change Order
CCG requests change order relating to re-vegitation of ROW (HOC 1.1) -
Erosion Change Order
CCG suffers damage and delay due to exceptionally adverse weather (HOC 1.3) -
Weather Delay
CCG suffers damage and delay due to exceptionally adverse weather (HOC 9) -
Floating Bridge Inaccesible (1/8-1/25)
Floating bridge at AR10 inaccessible due to rain (HOC 10) -
Locals Prevent Access
Access prevented by locals at KP77 (HOC 12) -
Period: to
Unforeseeable Rock Conditions
Unforeseeable rock conditions encountered at KP 43 (HOC 6) -
Weather Delay
CCG suffers damage and delay due to exceptionally adverse weather (HOC 9) -
Seeding Trial
CCG performs seeding trial at KP 2+500 -
Locals Prevent Access (3/1-3/9)
Access prevented by locals at KP77 (HOC 12) -
Period: to
Manual Seeding (Early March-Mid April)
CCG perfroms manual seeding between the mine and AR2 (HOC 1.1) -
Reinstatement/Re-Vegitation and MOU 2
CCG states belief that costs of reinstatement and re-vegetation were not included within MOU 2 lump sum price (HOC 1.1;1.2) -
Locals Prevent Access
Access prevented by locals at KP 85-KP 91 (HOC 12) -
Unforeseeable condtions
Unforeseeable physical conditions first encountered at Rianila River crossing (HOC 8) -
Locals Prevent Access (3/17-3/18)
Access prevented by locals at KP118 (HOC 12) -
Seeding Disapproval
SLI expresses dispproval of CCG's manual seeding and informs CCG it has contracted a hydroseeder (HOC 1.1) -
Re-Profiling Change Order
CCG requests change order relating to re-profiling of ROW (HOC 1.2) -
CCG Asserts Entitlement to Tranche Payments
CCG asserts it is entitled to both tranch payments, as delays were beyond its control (HOC 4) -
Locals Prevent Access (5/13-5/15)
Access prevented by locals at KP105 (HOC 12) -
Locals Prevent Acess (5/23-5/25)
Access prevented by locals at KP 105 (HOC 12) -
Period: to
Unforeseeable Rock Conditions
Unforeseeale rock conditions encountered at KP 77 (HOC 6) -
Period: to
Unforeseeable Rock Conditions
Unforeseeable rock conditions encountered at KP 104 (HOC 6) -
SLI Denies Tranche Payments
HOC 4 -
Seeding Dispute
CCG informs SLI that hydroseeding was performed at KP 7-10 only two days after manual seeding was performed, and thus CCG should not be liable for a backcharge for this hydroseeding (HOC 1.1) -
Hydrotesting Failure
Hydrotesting failure occurs along Section 5 (KP 44-KP-52) of the Slurry pipeline -
Hydrotesting Failure Delay (7/4-7/17)
Delays occur from KP 44-KP 52 due to hydrotesting failure (HOC 11) -
Locals Prevent Access (7/21-7/22)
Access prevented by locals at AR9 (HOC 12) -
Seeding Dispute
SLI informs CCG that its previous failed attempts at manual seeding are negaively affecting hydroseeding, such as at KP 9-10 (HOC 1.1) -
Rianila River complete
ESSAR informs CCG that Rianila River works are complete (HOC 8) -
Period: to
Locals Prevent Access
Access prevented by locals at SLI Site Plant (HOC 12) -
CCG Will Not Complete Construction by Set Date
CCG informs SLI that it will not achieve construction completion by date required for tranche payment (12/31), but asserts the reasons were beyond its control (HOC 4)