Bluenose II Announcements (and Delays)

  • Complete by March 2011 ($14.4 M)

    Complete by March 2011 at a cost of $14.4 million.
  • Complete by Summer 2011 ($14.7 M)

  • Complete by Spring 2012 ($14.7 M)

  • Complete by Summer 2012 ($15.9 M)

  • Complete by Summer 2012; launch by 2013 ($15.9 M)

  • Complete by Fall 2012 ($15.9 M)

  • LAUNCH DAY Complete by Summer 2013 ($15.9+ M)

  • BACK OUT OF WATER

  • Sea trials to begin Summer 2013. No estimate after that. ($15.9+ M)