December 22, 2014
Dakota Access, LLC presented idea for pipeline -
March 25, 2015
PSC deemed application complete -
July 25, 2016
Army Corps permit -
July 26, 2016
Standing Rock protest -
August 3, 2016
Embridge and Marathon invest in pipeline -
August 10, 2016
First arrest -
August 16, 2016
Restraining order -
August 24, 2016
Temporary Halt on construction of pipeline -
September 2016
Demonstrations held at pipeline entrance -
January 2016
Dakota Access Pipeline -
April 1, 2016
Creation of the Sacred Stone Camp -
April 29, 2016
Native Americans attend public forum -
October 2016
Construction of pipeline resumes -
June 11, 2016
NoDAPL fundraises nationwide -
July 15, 2016
Youth run for 2000 miles; North Dakota to DC -
November 2016
President addresses alternate routes for pipeline