Investigations begin for the clutha river
Investigations begin for the clutha river -
Roxburgh dam started
-
Huge investigations
Investgations into building more dams from lakes to seas -
Reports Submitted
Reports submitted about the enviromental effects of damm this is when alot of the protesting started -
Site Selected
Site Selected for the clutha dam -
Bull Dozers come in
Bull dozers come and clear a site for the dam -
Building Begins
The building begins on right side of the dam -
Building begins
Building begins on right side of the dam -
Government Agrees
Government agrees to the construction of the high dam -
fault Line discovered
fault line discovered and the dam is redesigned to cope -
1000 workers
work on the dam peaks with other 1000 workers on site -
gorge stabilization
Gorge stabilization work is complete -
Dam is Complete
dam is complete and reservoir is flooding cromwell gorge -
Dam is opend
The dam is officially opened -
New Owner
Contact energy shares owner ship if electrocorp -
New plans
Contact energy releases 5 new plans for dams on the clutha -
Withdraw plans
Contact energy withdraws plans for more dams