EXPANSION PROCESS

  • Project assigned to MIRMISA contarctor

    BGI Approve continue with the expansion tramits
  • Period: to

    Drawing, calculations, formats, tramits (Dec 2018 - Jan 2022)

  • Tramitology kickoff

    Tramit in different goverment offices
  • Period: to

    Water use feasibility (Mar 2019-Sep 2021)

  • Period: to

    Environmental Approval (Mar 2019 - Sep 2021)

  • Period: to

    Structural Security Tramit (Oct 2019-Dec 2021)

  • Period: to

    COVID19 Period (Mar 2020 - Jan 2021)

    GOVERMENT PROCESS WAS STOPED
  • land use update

  • Alignment & Official number

  • Civial Protection Approval

    Emergency plan project
    Approval by goverment office
  • Municipality Office final rev.

    The Alcaldia GAM receive the 25 requirements.
  • Municipality Office detect discrepancies

    Municipality Office detected discrepancies between Property taxes against Construction Permit square meters (2000mt2)
  • Tramit rejected by (Structural issues & built area)

  • Legal status review by Lawyers (Grahamm)