Project assigned to MIRMISA contarctor
BGI Approve continue with the expansion tramits -
Period: to
Drawing, calculations, formats, tramits (Dec 2018 - Jan 2022)
-
Tramitology kickoff
Tramit in different goverment offices -
Period: to
Water use feasibility (Mar 2019-Sep 2021)
-
Period: to
Environmental Approval (Mar 2019 - Sep 2021)
-
Period: to
Structural Security Tramit (Oct 2019-Dec 2021)
-
Period: to
COVID19 Period (Mar 2020 - Jan 2021)
GOVERMENT PROCESS WAS STOPED -
land use update
-
Alignment & Official number
-
Civial Protection Approval
Emergency plan project
Approval by goverment office -
Municipality Office final rev.
The Alcaldia GAM receive the 25 requirements. -
Municipality Office detect discrepancies
Municipality Office detected discrepancies between Property taxes against Construction Permit square meters (2000mt2) -
Tramit rejected by (Structural issues & built area)
-
Legal status review by Lawyers (Grahamm)