PO was received
277C655 / 300 pieces / $1.104
277C656 / 300 pieces / $2.622
277C627 / 175 pieces / $2.694
277C628 / 175 pieces / $5.393
Arrival FEJV date 20201101 -
Internal "Kick-Off" was submitted
-
Upload PNs in JBA system
-
Upload RM Codes
-
Issue PO for RM to Sanhaw
Ø5.5, Ø8.5, Ø5.7, Ø9.0mm -
Issue PO for RM to SG Mx
Ø5.5 & Ø5.7mm -
Reception RM from SG Mx
Ø5.5 & Ø5.7mm -
Start 1° trial & Plan collect data SG Mx
Ø5.5 & Ø5.7mm -
Manufacturing PPAP samples
From March/01 To March 05
Ø5.5 & Ø5.7mm -
Fatigue Test at ASBG Mx
Performe Fatigue Test (C655 & C627) 5M cycles
From March/08 To March/12 -
Available samples to be shipped / Delivery Location: China
SG Mx Samples -
PPAP paperwork
277C655
277C627 -
Reception RM from Sanhaw
Ø5.5, Ø8.5, Ø5.7, Ø9.0mm -
Start 1° trial & Plan collect data Samhaw
From March/31 To April 06 -
Manufacturing PPAP samples
Ø 8.5 & Ø 9.0mm
From April/06 To April/12 -
Available samples to be shipped / Delivery Location: China
Samhaw samples -
Fatigue Test at Plymouth ITC
From April/12 To April/16 -
PPAP paperwork
277C656
277C628