B-Ligon Pharmacy System

By ln2543
  • Week 1

    Week 1
    o meet/consultation
    o give demo
    o Access needs/ expectations
    o Take a tour of company
  • Week 2

    Week 2
    o project charter
    o scope
    o establish payment schedule
    o timeline and sign the pre- contract
  • Week 3

    Week 3
    o Analyze current workflow and discuss how our systemwill effect it
    o Get feedback from hospital before making a final contract
  • Week 4

    Week 4
    o finalized plan for installation
    o sign official contract
    o take up 1st down payment
     2nd payment at installation
     3rd payment after go-life
     Reoccurring payments at the beginning of each month after June
  • November - December

    November - December
    • preparation of orders within our company
    • contact installers and trainers and prepare them for installation process
    • tie all loose ends on paperwork
  • January - March

    January - March
    • Installation process begins (3-months)
    o Customizing
    o Adding programs
    o Transferring data
    • 2nd payment due
  • March

    March
    • Week 1- training for 4 days and go live on the 5th day
    • 3rd payment due
  • June

    June
    • Post install audit