Preparing Site
Day 1 to 14 -
Period: to
Plumbing
Day 15 to 18 -
Period: to
Slab
Day 19 to 21 -
Period: to
Frame
Day 22 to 50 -
Period: to
Windows
Day 51 to 53 -
Period: to
Roof
Day 51 to 54 -
Period: to
Cladding
Day 55 to 61 -
Period: to
Electrical
Day 62 -
Period: to
Internal Wall Lining
Day 63 to 67 -
Period: to
Water Proofing
Day 68 -
Period: to
Tiling Wet Areas
Day 69 to 74 -
Period: to
Fixtures and Fittings
Day 75 to 78 -
Period: to
Flooring
Day 79 -
Period: to
Painting Internally
Day 80 to 88 -
Period: to
Painting Externally
Day 80 to 86 -
Period: to
Landscaping and Driveway
Day 89 to 94 -
Period: to
Fence
Day 89 to 92