Timeline of house build

  • Period: to

    Preparing Site

    Day 1 to 14
  • Period: to

    Plumbing

    Day 15 to 18
  • Period: to

    Slab

    Day 19 to 21
  • Period: to

    Frame

    Day 22 to 50
  • Period: to

    Windows

    Day 51 to 53
  • Period: to

    Roof

    Day 51 to 54
  • Period: to

    Cladding

    Day 55 to 61
  • Period: to

    Electrical

    Day 62
  • Period: to

    Internal Wall Lining

    Day 63 to 67
  • Period: to

    Water Proofing

    Day 68
  • Period: to

    Tiling Wet Areas

    Day 69 to 74
  • Period: to

    Fixtures and Fittings

    Day 75 to 78
  • Period: to

    Flooring

    Day 79
  • Period: to

    Painting Internally

    Day 80 to 88
  • Period: to

    Painting Externally

    Day 80 to 86
  • Period: to

    Landscaping and Driveway

    Day 89 to 94
  • Period: to

    Fence

    Day 89 to 92