-
Tiki-Hut Inc. applied for Building Permit
. -
Period: to
Construction Timeline
Tiki Hut Resturaunt -
Revision 2 made to drawings
made to drawings -
Original bid submission by San Fernando Builders
. -
Plans Issued
. -
Tiki-Hut Inc. executed a lump sum contract with San Fernando Builders
. -
Letter of Commencement, Notice to Proceed from Tiki-Hut Inc.
. -
Original date for lump sum contract of $2,150,500 to commence
-
Building Permit obtained by Tiki-Hut Inc.
-
San Fernando Builders mobilized to the site to start work, No site work completed by Dirt Doctors, Inc.
-
San Fernando Job Issue Log claims 46 separate issues that occurred on project
-
Original 160 day completion date for project
-
Revised Project Completion Date
-
Request for Change Orders was submitted and the amounts approved. Note substantial overlap with Job Issue Log claims.
-
Revision 20 made to drawings
-
Project completed 4 months and 2 weeks later than planned