Tiki Hut Resturaunt Construction Timeline

  • Tiki-Hut Inc. applied for Building Permit

    .
  • Period: to

    Construction Timeline

    Tiki Hut Resturaunt
  • Revision 2 made to drawings

    made to drawings
  • Original bid submission by San Fernando Builders

    .
  • Plans Issued

    .
  • Tiki-Hut Inc. executed a lump sum contract with San Fernando Builders

    .
  • Letter of Commencement, Notice to Proceed from Tiki-Hut Inc.

    .
  • Original date for lump sum contract of $2,150,500 to commence

  • Building Permit obtained by Tiki-Hut Inc.

  • San Fernando Builders mobilized to the site to start work, No site work completed by Dirt Doctors, Inc.

  • San Fernando Job Issue Log claims 46 separate issues that occurred on project

  • Original 160 day completion date for project

  • Revised Project Completion Date

  • Request for Change Orders was submitted and the amounts approved. Note substantial overlap with Job Issue Log claims.

  • Revision 20 made to drawings

  • Project completed 4 months and 2 weeks later than planned