Savvy High School Building Plan By laurashumate Jan 1, 2013 Grading and Site Preparation Jan 6, 2013 Groundbreaking Ceremony! We will dig the first bit of ground to start construction! Feb 7, 2013 Lay-off and dig footers Feb 20, 2013 Pour Footers Mar 10, 2013 Lay several courses of block for foundation Mar 20, 2013 Frame and roof building Apr 1, 2013 Do initial plumbing rough-in before pouring concrete slab Apr 7, 2013 Pour concrete slab inside block work Apr 25, 2013 Rough in plumbing, heating, ventilation, and air conditioning May 1, 2013 Finish exterior and interior of building Jun 5, 2013 Finish plumbing, heating, ventilation and wiring for technology Aug 10, 2013 Finish parking lots, sidewalks, landscaping, etc. Aug 20, 2013 Obtain Certificate of Occupancy from Building Inspections Department Aug 28, 2013 Furnish, set up technology