Grading and Site Preparation
-
Groundbreaking Ceremony!
We will dig the first bit of ground to start construction! -
Lay-off and dig footers
-
Pour Footers
-
Lay several courses of block for foundation
-
Frame and roof building
-
Do initial plumbing rough-in before pouring concrete slab
-
Pour concrete slab inside block work
-
Rough in plumbing, heating, ventilation, and air conditioning
-
Finish exterior and interior of building
-
Finish plumbing, heating, ventilation and wiring for technology
-
Finish parking lots, sidewalks, landscaping, etc.
-
Obtain Certificate of Occupancy from Building Inspections Department
-
Furnish, set up technology