Dam proposed on the Deep River
-
U.S. Congress authorized $11 million for construction for Randleman Lake
-
Environmental Impact report done
-
Local government supports Randleman project
-
The Piedmont Triad Regional Water Authority was formed
-
PTRWA purchased land of dam and lake
-
Water quality acceptable for public
-
PTRWA prepared wetland migration
-
Design on dam began
-
Study conducted questioning the effects of the Seaboard Chemical plant
-
Water guidelines adhere to Federal Clean Water Act
-
Contruction on the Dam began
-
Planning the water treatment plant, pump stations and pipelines began
-
Set date to start constructing the water treatment plant
-
Vote to open lake by March 1, 2010
-
Water quality equal to other Greensboro water supplies
-
Randleman Reservoir opens for fishing and boating
-
Water is flowed out to consumers
-
1,4 Dioxane is confirmed in water supply