Construction Starts
The house starts to be built! -
Period: to
Preparing site: 2 weeks
-
Period: to
Plumbing: 3 days
-
Period: to
Slab: 2 days
-
Period: to
Frame: 4 weeks
-
Period: to
Windows: 2 days
-
Period: to
Roof: 3 days
-
Period: to
Cladding frame: 1 week
-
Period: to
Electrical: 8 hours
8 hours is about an average working day for a builder so this is counted as one days work. -
Period: to
Internal wall lining: 4 days
-
Period: to
Waterproofing: 1 day
-
Period: to
Tiling wet areas: 5 days
-
Period: to
Fixtures and fittings: 3 days
-
Period: to
Flooring timber: 6 hours
This will be done within the day so it is one days work. -
Period: to
Carpets: 8 hours
This is one whole days work. -
Period: to
Painting Internally: 8 days
-
Period: to
Painting Externally: 6 days
-
Period: to
Landscaping and driveway: 5 days
-
Period: to
Fence: 3 days
-
Construction Finishes
The house is done!